Alaska agency boosting gas line asks skeptical Legislature to consider investing up to 0M


Alaska Gasline Development Corp. president Frank Richards, left, and Matt Kissinger, venture development manager at AGDC, discuss the proposed $44 billion gas pipeline project with state legislators on Wednesday, April 23, 2025. (Sean Maguire / ADN)

JUNEAU — The state agency advocating for a $44 billion gas line in Alaska is asking the Legislature to consider investing up to $800 million in the long-sought but faltering megaproject.

There has been renewed interest in building an 800-mile gas pipeline from the North Slope since President Donald Trump announced his strong support for the project. Several Asian nations have shown an interest in investing in the pipeline and buying gas from Alaska, but no concrete deals have yet been signed.

Gov. Mike Dunleavy and Alaska’s three-member, all-Republican congressional delegation have been bullish on the Alaska LNG project. Some lawmakers have been equally optimistic, but multiple legislators said they remain skeptical that the pipeline will be built, particularly on the fast timeline touted by the project’s new private developer.

Frank Richards, president of Alaska Gasline Development Corp., told legislators this week about the upsides of the project. It has been fully permitted and is eligible for $28 billion in federal loan guarantees, he said.

Advertisement

Delegates from South Korea and Thailand are set to come to Alaska soon to study the project, AGDC officials said this week. Additionally, the Trump administration is urging leaders of several Asian nations to commit to the pipeline with representatives set to attend a June summit in Alaska, The New York Times reported.

[South Korea and other Asian countries plan visits to the state as they eye Alaska LNG project]

The renewed interest in the pipeline comes after AGDC — the state agency leading the project — announced in January that Glenfarne had signed on to become its lead developer.

The terms of AGDC’s deal with Glenfarne, a New York-based company, remain confidential. But AGDC told lawmakers this week that Glenfarne agreed to take a 75% stake in exchange for bringing the project to a final investment decision — a pivotal step in completing a megaproject.

Richards said Wednesday that Glenfarne had recently “suspended” calls for an Alaska development agency to provide $50 million as an insurance policy for remaining engineering and design work. Instead, Richards said Glenfarne would be willing to use private capital to complete that work, which is estimated to cost $150 million.

Advertisement

‘It is in our future’

In recent months, some lawmakers have been buoyed by the prospects for the project.

Anchorage GOP Rep. Chuck Kopp penned an opinion piece in the Daily News encouraging Alaskans to “shake the cynicism off.” Fellow Anchorage Republican Rep. Mia Costello introduced a legislative resolution that urges support for “the rapid advancement” of the pipeline.

“We really will be having a gas line. It is in our future,” Costello said at a Tuesday media conference.

Still, multiple lawmakers said while they support the pipeline, they have lingering doubts and questions. Some legislators have been skeptical about the project’s costs and timelines; others have questioned why Glenfarne, a relatively new player in the oil and gas sector, was chosen as the lead developer.

Richards said other offers were discussed, but Glenfarne got the tick of approval from AGDC’s board and investment bank Goldman Sachs.

Advertisement

Some lawmakers have bristled at what they say is the Legislature’s limited oversight of the project.

In 2014, the Legislature approved Senate Bill 138, which granted AGDC broad authority to develop the pipeline.

Republican former House Speaker Mike Chenault, a current AGDC board member, said the agency’s independence was by design. He said that gives AGDC the ability to make decisions in a timely matter.

“I believe that if the Legislature gets involved, that this project will go away,” he said.

With Southcentral Alaska facing a looming shortfall of natural gas from Cook Inlet, the pipeline has been touted as a way to secure gas supply for Alaska in the long term. But the project is also being discussed as a way to fill state coffers.

Advertisement

Officials at AGDC said the state’s current stake in the project could potentially raise hundreds of millions of dollars per year in new revenue, but that is still set to be negotiated with Glenfarne and any other potential investors.

There is an opportunity for Alaska to invest substantially more in the project to collect more revenue for the state, Richards said.

“The big question for the state of Alaska going forward is really going to be around that equity financing,” he said Wednesday to a joint legislative committee.

The project has recently been split into phases. The first phase would see an 807-mile gas pipeline built from the North Slope to Nikiski. The second phase would see plants built to treat gas and prepare it for export.

Richards told lawmakers that the state, Alaska Native corporations, Alaska businesses and individual Alaskans could invest up to 25% in those subprojects. For the pipeline, that would cost roughly $800 million. For the pipeline and two plants, the cost would be over $3.5 billion, AGDC board members said earlier in the month.

Advertisement

The Legislature is currently grappling with strained revenue and a dire fiscal outlook, making it unlikely that it could fund the 25% stake in the pipeline, lawmakers said.

Anchorage Republican Sen. Cathy Giessel said that she had heard little interest from lawmakers for the state to put “money into this project.” Giessel, chair of the Senate Resources Committee, said “$800 million, of course, is an absurd amount.”

Timing, tailwinds and wariness

Project timelines have also been greeted with skepticism by veteran legislators.

Richards told lawmakers this week that a final investment decision could be reached by the end of the year. A pipeline could be constructed and delivering gas for Alaskans by 2030 or 2031, he said.

During a joint legislative committee hearing, House Speaker Bryce Edgmon said that there seemed to be “missing key ingredients” in answers to legislators’ questions from AGDC. Edgmon, a Dillingham independent, suggested that the 2031 timeline seemed “more aspirational than it is reality.”

Advertisement

The costs of the project have also come under scrutiny. The full gas line project was estimated in 2023 to cost $44 billion, AGDC board members said. The pipeline itself was expected then to cost just under $11 billion.

Rep. Zack Fields, D-Anchorage, said that the trans-Alaska pipeline was completed in 1977 at a cost of $8 billion. He said that the gas pipeline is expected to cost 37% more than TAPS, but that inflation has increased prices more than five-fold over the past 48 years.

Fields asked how that cost estimate for the gas pipeline could be “plausible.”

Warren Christian, an AGDC board member, said the project’s costs were carefully calculated by ExxonMobil.

An updated cost estimate is expected after engineering and design work is completed, AGDC officials said.

Advertisement

While pipeline discussions continue, concrete plans have been advancing to import gas for Southcentral Alaska. Gas line boosters said the project could be a viable long-term fix for the state’s energy needs.

Veteran legislators say they’ve heard that before.

Anchorage Democratic Sen. Bill Wielechowski said there seemed to be some positive “tailwinds” behind the project, citing interest from the Trump administration and in Asia. But Wielechowski estimated this was the eighth version of the pipeline he’s heard pitched during his 18-year tenure in the Legislature.

“I’m a bit wary at this point, just based on promises we’ve heard in the past,” he said. “New administrations, new people come in and it sounds great, and then, for whatever reason, it just doesn’t work.”

As an example, he pointed to TransCanada. In 2008, the Legislature approved paying up to $500 million for the Calgary-based company to help with pre-construction costs. Seven years later, the Legislature appropriated $64 million to buy out TransCanada’s stake in the project.

Advertisement

Wielechowski said the state should consider investing in the pipeline to raise more state revenue for Alaska. But echoing many in the Capitol, he remained somewhat doubtful the project would come to fruition.

“I want it to happen. I share the sentiment that I think many Alaskans share — I’ll believe it when I see it,” he said.





Source link

Alaska

Dozens of vehicle accidents reported, Anchorage after-school activities canceled, as snowfall buries Southcentral Alaska

Published

on

Dozens of vehicle accidents reported, Anchorage after-school activities canceled, as snowfall buries Southcentral Alaska


ANCHORAGE, Alaska (KTUU) – Up to a foot of snow has fallen in areas across Southcentral as of Tuesday, with more expected into Wednesday morning.

All sports and after-school activities — except high school basketball and hockey activities — were canceled Tuesday for the Anchorage School District. The decision was made to allow crews to clear school parking lots and manage traffic for snow removal, district officials said.

“These efforts are critical to ensuring schools can safely remain open [Wednesday],” ASD said in a statement.

The Anchorage Police Department’s accident count for the past two days shows there have been 55 car accidents since Monday, as of 9:45 a.m. Tuesday. In addition, there have been 86 vehicles in distress reported by the department.

Advertisement
Snow measuring up to 17 inches deep in Anchorage, Alaska, on Jan. 6, 2026.(Alaska’s News Source)

The snowfall — which has brought up to 13 inches along areas of Turnagain Arm and 12 inches in Wasilla — is expected to continue Tuesday, according to latest forecast models. Numerous winter weather alerts are in effect, and inland areas of Southcentral could see winds up to 25 mph, with coastal areas potentially seeing winds over 45 mph.

Up to a foot or more of snow has fallen across Southcentral Alaska, with more snow expected...
Up to a foot or more of snow has fallen across Southcentral Alaska, with more snow expected through the day.(Alaska’s News Source)

Some areas of Southcentral could see more than 20 inches of snowfall by Wednesday, with the Anchorage and Eagle River Hillsides, as well as the foothills of the Talkeetna Mountain, among the areas seeing the most snowfall.

See a spelling or grammar error? Report it to web@ktuu.com



Source link

Advertisement
Continue Reading

Alaska

Yundt Served: Formal Charges Submitted to Alaska Republican Party, Asks for Party Sanction and Censure of Senator Rob Yundt

Published

on

Yundt Served: Formal Charges Submitted to Alaska Republican Party, Asks for Party Sanction and Censure of Senator Rob Yundt


Sen. Rob Yundt

On January 3, 2026, Districts 27 and 28 of the Alaska Republican Party received formal charges against Senator Rob Yundt pursuant to Article VII of the Alaska Republican Party Rules.

According to the Alaska Republican Party Rules: “Any candidate or elected official may be sanctioned or censured for any of the following
reasons:
(a) Failure to follow the Party Platform.
(b) Engagement in any activities prohibited by or contrary to these rules or RNC Rules.
(c) Failure to carry out or perform the duties of their office.
(d) Engaging in prohibited discrimination.
(e) Forming a majority caucus in which non-Republicans are at least 1/3 or more of the
coalition.
(f) Engaging in other activities that may be reasonably assessed as bringing dishonor to
the ARP, such as commission of a serious crime.”

Advertisement

Party Rules require the signatures of at least 3 registered Republican constituents for official charges to be filed. The formal charges were signed by registered Republican voters and District N constitutions Jerad McClure, Thomas W. Oels, Janice M. Norman, and Manda Gershon.

Yundt is charged with “failure to adhere and uphold the Alaska Republican Party Platform” and “engaging in conduct contrary to the principles and priorities of the Alaska Republican Party Rules.” The constituents request: “Senator Rob Yundt be provided proper notice of the charges and a full and fair opportunity to respond; and that, upon a finding by the required two-thirds (2/3) vote of the District Committees that the charges are valid, the Committees impose the maximum sanctions authorized under Article VII.”

If the Party finds Yundt guilty of the charges, Yundt may be disciplined with formal censure by the Alaska Republican Party, declaration of ineligibility for Party endorsement, withdrawal of political support, prohibition from participating in certain Party activities, and official and public declaration that Yundt’s conduct and voting record contradict the Party’s values and priorities.

Reasons for the charges are based on Yundt’s active support of House Bill 57, Senate Bill 113, and Senate Bill 92. Constituents who filed the charges argue that HB 57 opposes the Alaska Republican Party Platform by “expanding government surveillance and dramatically increasing education spending;” that SB 113 opposes the Party’s Platform by “impos[ing] new tax burdens on Alaskan consumers and small businesses;” and that SB 92 opposes the Party by “proposing a targeted 9.2% tax on major private-sector energy producer supplying natural gas to Southcentral Alaska.” Although the filed charges state that SB 92 proposes a 9.2% tax, the bill actually proposes a 9.4% tax on income from oil and gas production and transportation.

Many Alaskan conservatives have expressed frustration with Senator Yundt’s legislative decisions. Some, like Marcy Sowers, consider Yundt more like “a tax-loving social justice warrior” than a conservative.

Advertisement



Source link

Continue Reading

Alaska

Pilot of Alaska flight that lost door plug over Portland sues Boeing, claims company blamed him

Published

on

Pilot of Alaska flight that lost door plug over Portland sues Boeing, claims company blamed him


The Alaska Airlines captain who piloted the Boeing 737 Max that lost a door plug over Portland two years ago is suing the plane’s manufacturer, alleging that the company has tried to shift blame to him to shield its own negligence.

The $10 million suit — filed in Multnomah County Circuit Court on Tuesday on behalf of captain Brandon Fisher — stems from the dramatic Jan. 5, 2024 mid-air depressurization of Flight 1282, when a door plug in the 26th row flew off six minutes after take off, creating a 2-by-4-foot hole in the plane that forced Fisher and co-pilot Emily Wiprud to perform an emergency landing back at PDX.

None of the 171 passengers or six crew members on board was seriously injured, but some aviation medical experts said that the consequences could have been “catastrophic” had the incident happened at a higher altitude.

Leani Benitez-Cardona, NTSB aerospace engineer, and Matthew Fox, NTSB chief technical advisor for materials, unpacking the door plug Sunday from Alaska Airlines flight 1282, a Boeing 737-9 MAX, in the materials laboratory at NTSB headquarters in Washington, D.C.NTSB

Fisher’s lawsuit is the latest in a series filed against Boeing, including dozens from Flight 1282 passengers. It also names Spirit AeroSystems, a subcontractor that worked on the plane.

Advertisement

The lawsuit blames the incident on quality control issues with the door plug. It argues that Boeing caught five misinstalled rivets in the panel, and that Spirit employees painted over the rivets instead of reinstalling them correctly. Boeing inspectors caught the discrepancy again, the complaint alleges, but when employees finally reopened the panel to fix the rivets, they didn’t reattach four bolts that secured the door panel.

The complaint’s allegations that Boeing employees failed to secure the bolts is in line with a National Transportation Safety Board investigation that came to the conclusion that the bolts hadn’t been replaced.



Source link

Advertisement
Continue Reading

Trending