Seattle, WA
SDOT Sprints Toward the End of the Move Seattle Era – The Urbanist
With a $1.45 billion transportation levy proposal in front of the Seattle City Council, attention has turned toward future investments and what they mean for the city’s collective mobility priorities. But behind the scenes, the Seattle Department of Transportation (SDOT) is quietly getting projects out the door in what is on track to be the busiest year for transportation projects in Seattle, ever. The goal is to finish strong on the current Move Seattle Levy, approved in 2015, and make a compelling case for the next transportation levy, which makes up around a third of SDOT’s entire budget. But in so doing, SDOT is also showing how the department has evolved in the past nine years.
So far this year, SDOT has solicited bids from contractors on a huge array of projects, including nearly 10 seismic upgrades on bridges around the city, sidewalk projects, crossing improvements, and a number of big projects that have been in the pipeline for a long time — including the RapidRide J corridor project, the critical first phase of the Beacon Hill bike route, the next phase of Rainier Avenue transit lanes, and upgrades for King County Metro’s Route 40.
All of these projects are on different construction timelines, and different levels of visibility for everyday city residents, but they’re all part of the push at the end of the levy to get things out the door.
“The average number of construction starts we’ve had over the last few years, for contracted projects, is one a month,” SDOT Director Greg Spotts, who has been heading the department since fall of 2022, told The Urbanist. “January, February, March and April, we’ve had eight, so we’ve doubled it to two a month. That’s a step change. That’s not a incremental change. And I’m very proud of the team for doing that. And I think the pace is going to increase even further, in terms of the number of construction starts a month, most of which are levy funded projects, all the way through the end of this year.”

Spotts touts the project delivery machine that the department has been able to create in recent years as producing the results that Seattle residents are seeing in their neighborhoods, something that also extends to smaller projects, delivered by SDOT’s own crews: things like new crosswalks and all-way stops installed near many of Seattle’s elementary schools in the past year, and the pilot bike lane barriers being rolled out in existing protected bike lanes around the city.
“I have made a very significant effort to increase the tempo of how we get these projects through design, how we conduct community outreach in a way that’s efficient for us and the community members, and how we make decisions and confidently carry on and make the next round of decisions to get things into construction,” Spotts said.
But a big part of the 2024 push is attributable to the 2015 levy’s ambitious goals, which pushed the department to continually look for new resources to get closer. Even if Seattle wasn’t able to deliver seven full transit corridor projects, due in part to a lack of federal matching dollars, having that goal ensured that upgrades to the Route 40, 44, and 48 all moved forward in some capacity. Even though the city won’t hit its goal of implementing 110 miles of bike infrastructure, projects like the Georgetown-to-Downtown bike route likely wouldn’t have happened on their current timelines without that goal.
“There’s a pretty broad consensus within SDOT that we got off to a slow start on the Levy to Move Seattle, and perhaps one of the reasons why was there was kind of a assumption that existing staff could do the job. And if you just almost tripled the size of the levy, it would have made more common sense that you need to staff up,” Spotts said.
In many ways, in the area of project delivery, today’s Seattle Department of Transportation is the one that voters were promised in 2015… it just took several more years than initially expected to get there.
“SDOT’s quite a bit larger in headcount than we were in 2015-2016. And we have a very sophisticated capital projects division and project development division, who are, not just larger, but we’ve actually developed talent during this period,” Spotts continued. “We have people who are much more experienced, who are experienced working with each other; we’ve refined internal systems for collaboration and coordination. So I really believe that we have a capital projects delivery machine that didn’t exist at nearly this throughput capacity back when the Levy to Move Seattle was started.”
But Mayor Bruce Harrell’s levy renewal proposal, getting its first public hearing today at the Seattle City Council, is less ambitious in its goals and includes fewer guardrails around what specifically the city is expected to spend money on. When Move Seattle included baseline funding requirements in the city’s budget for its three main categories — safe routes, congestion relief, and maintenance and repair — this levy only specifies anticipated spending levels, no minimum requirements. Project lists are currently fairly vague, though there are some specific commitments, including one to construct 250 blocks of new sidewalks by the midpoint of the levy in 2029.
“One of the lessons we learned from the Levy to Move Seattle was to be more cautious about making early commitments that rely on optimistic assumptions about how much grant funding we will receive,” SDOT spokesperson Ethan Bergerson told The Urbanist. Making fewer concrete commitments is a way to ensure the department doesn’t go over its skis, but it also paints a less compelling vision for the city’s transportation vision, and is one factor behind a large push by transportation advocates to make the next levy much bigger and more ambitious.
And then there’s the issue of what happens later this year, with all of these projects out the door and the fate of the next levy very much up-in-the-air. Will a lack of projects in the pipeline lead to a similar lag in project delivery like the city saw at the start of Move Seattle? Spotts says no, adding that they’re thinking differently about this than they have in the past.
“We’re exploring whether there’s some projects that the current levy can’t afford to construct, but could afford to complete design on,” Spotts said. “We want to have basket of projects that could be shovel ready for the next levy.” The department has already received grant funding for two corridor repaving projects, one on E Marginal Way S north of the South Park Bridge, and another on Roosevelt Way NE from NE 92 St to Pinehurst Way NE. Those projects, expected to have multimodal components, are set to be the first to move forward under the new levy.
Spotts also touts the planned goal of protecting 30% of the existing bike lanes in the city with more substantive barriers. “We think we could take that Better Bike Barrier program, and scale it with funds from the new levy. We could be dropping Toronto [style] barriers into existing bike lanes that currently have the paint and post, and that’s something we can do with city forces.”
What SDOT seems to be showing the city in 2024 is that the department is prepared to hit the ground running if voters approve the next levy. But what’s missing is how that levy will actually push the City towards achieving a collective vision that can endure no matter who’s in the Mayor’s Office or at the top of SDOT.
The Seattle City Council is holding the first of two public hearings on Mayor Bruce Harrell’s transportation levy proposal today at 4:30pm. You can sign up to testify virtually starting at 3:30pm, or submit written comments anytime, here.
For more information, The Urbanist has analyzed the mayor’s levy proposal in a series of articles:

Ryan Packer lives in the Summit Slope neighborhood of Capitol Hill and has been writing for the The Urbanist since 2015. They report on multimodal transportation issues, #VisionZero, preservation, and local politics. They believe in using Seattle’s history to help attain the vibrant, diverse city that we all wish to inhabit. Ryan’s writing has appeared in Capitol Hill Seattle Blog, Bike Portland, and Seattle Bike Blog, where they also did a four-month stint as temporary editor.
Seattle, WA
FOLLOWUP: City Light’s Brace Point project now one-third complete
If you live in the Fauntleroy-area neighborhood where Seattle City Light is working on long-needed underground repairs and updates, Brace Point, you’ve probably closely followed their progress. For those who haven’t, here’s the latest of SCL’s periodic updates:
Seattle City Light contractors continue to work on the underground electrical infrastructure serving the Brace Point neighborhood. They are installing new duct banks, conduits, cables, vaults, and streetlights. The new infrastructure will help reduce the risk of outages and improve service for residents.
Underground civil construction is approximately 32% complete. Our crews have installed 3,470 linear feet of conduit and 13 underground electrical vaults. We expect to finish most civil construction by the end of 2026. After that, crews will focus on cleaning staging areas and restoring the project area to the same, if not better, condition.
You can reach our team at bracepointcable@stephersonassociates.com or 206-312-0021.
If you would like to talk to a member of the project team in person, you can find us in the upstairs meeting room at the Southwest Branch of the Seattle Public Library on Wednesday, April 8 from 12-1 PM.
Current work areas:
Southwest Brace Point Drive: Crews are working near the intersection of 46th Ave. SW and SW Brace Point Drive.
47th Ave. Southwest: Crews are working north along 47th Ave. SW near the intersection of 46th Ave. SW and SW Roxbury St. Please drive carefully through this intersection and expect changing traffic patterns as the work progresses.
Longer than usual delays: Concrete pours are scheduled to occur on Wednesdays from 8 AM – 2 PM for the remainder of the project. Due to the narrow streets, trucks may have to park in the right-of-way. Please plan for longer than normal delays during these times.
Pedestrian trail: Crews are running new conduit and replacing the streetlight on the trail between 47th Ave.
Southwest to 48th Ave. Southwest. The trail is closed and expected to reopen in mid-April, once crews have finished the foundation for the new light pole. They will restore any areas disturbed by the project to City standards.Upcoming work areas
46th Ave. Southwest: After crews complete work on Brace Point Drive, they will start utility work on the segment of 46th Ave SW between Brace Point Drive and the intersection of SW Roxbury St and 47th Ave SW.
47th Ave. Southwest: This spring, crews will start working near the south end of 47th Ave. SW and work north towards the intersection of SW 98th St.
The work finally started last fall, five years after the originally projected start date.
Seattle, WA
Video shows man attempt to push stranger in front of train in Seattle
Video shows man allegedly try to push stranger in front of train
Immediate mental health help is available in the U.S. by calling or texting 988 to reach the Suicide & Crisis Lifeline.
A man was charged with attempted murder after a video appeared to show him attempting to push a person in front of a moving train. The moment was captured on surveillance camera footage.
The incident occurred on the Northgate light rail station in Seattle on March 19, as a train was pulling up, according to Storyful.
The video shows a man wearing a black hoodie standing behind a stranger who was on his phone. The man watches the train tracks, and as the train comes into view in the video, the man then pushes the victim, who stumbles forward. When the victim regains his balance, the suspect attempts to push him again and then flees the scene. The victim was able to hold his footing and appears to follow the man.
See shocking video of the attack
Suspect ordered mental health evaluation
Detectives later found the suspect, identified as Elisio Melendez, at a “mental health community facility where he lived,” according to the King County Prosecutor’s Office.
Melendez was later charged with attempted murder in the second degree and is being held on a $750,000 bail, according to King County arrest records obtained by USA TODAY.
Melendez, whose defense team stated has a history of mental illness, reported KOMO News, was ordered to undergo mental health evaluations during his arraignment on Tuesday, March 31.
USA TODAY has reached out to Melendez’s attorney for comment.
Immediate mental health help is available in the U.S. by calling or texting 988 to reach the Suicide & Crisis Lifeline.
Julia Gomez is a Trending reporter for USA TODAY and covers popular toys, space phenomena, scientific studies, natural disasters, holidays, and trending news. Connect with her on LinkedIn, X, Instagram, and TikTok: @juliamariegz, or email her at jgomez@gannett.com.
Seattle, WA
I-5 blocked near Chehalis, WA due to barricaded suspect
Standoff blocks I-5 in Chehalis
Washington State Patrol is in a standoff with a barricaded suspect that attempted to flee from troopers in Lewis County on Thursday.
CHEHALIS, Wash. – All lanes of I-5 are fully blocked near Chehalis due to a barricaded suspect on the freeway.
Washington State Patrol and law enforcement engaged in a standoff on I-5 near Chehalis. (Washington State Patrol)
What we know:
Washington State Patrol troopers are currently engaged in a standoff with a suspect that fled from Mason and Thurston County troopers.
Northbound and southbound I-5 are fully blocked just south of Chehalis, near the U.S. Route 12 interchange. Traffic is being diverted just before US-12.
The suspect’s vehicle was reportedly spiked on Rush Road in Chehalis before coming to a stop on southbound I-5. There is only one person in the vehicle, and troopers are still negotiating with the suspect.
Drivers are asked to avoid the area and expect delays.
What we don’t know:
It’s currently unknown what led up to the pursuit.
This is a developing story. Check back for updates.
MORE NEWS FROM FOX 13 SEATTLE
7 teens involved in deadly Bremerton car crash
Controversy continues to surround CCTV cameras in Seattle
Drivers navigate delays as WSDOT works to clear Bellingham, WA landslide
Budget cuts could impact access to Washington’s public lands
WA judge gives man longest big game sentence in decade for elk killing spree
To get the best local news, weather and sports in Seattle for free, sign up for the daily FOX Seattle Newsletter.
Download the free FOX LOCAL app for mobile in the Apple App Store or Google Play Store for live Seattle news, top stories, weather updates and more local and national news.
The Source: Information in this story came from the Washington State Patrol.
-
Culture1 week agoWil Wheaton Discusses ‘Stand By Me’ and Narrating ‘The Body’ Audiobook
-
South-Carolina6 days agoSouth Carolina vs TCU predictions for Elite Eight game in March Madness
-
Culture1 week agoWhat Happens When We Die? This Wallace Stevens Poem Has Thoughts.
-
Miami, FL1 week agoJannik Sinner’s Girlfriend Laila Hasanovic Stuns in Ab-Revealing Post Amid Miami Open
-
Minneapolis, MN1 week agoBoy who shielded classmate during school shooting receives Medal of Honor
-
Education1 week agoVideo: Transgender Athletes Barred From Women’s Olympic Events
-
Vermont6 days ago
Skier dies after fall at Sugarbush Resort
-
Politics6 days agoTrump’s Ballroom Design Has Barely Been Scrutinized

