The Alaska Railroad plans to spend $80 million to exchange and develop the previous cruise ship dock in Seward, setting the stage to carry bigger cruise ships and extra vacationers to Southcentral Alaska. A $25 million freight dock growth can be within the works.
The brand new dock will lengthen near 1 / 4 of a mile into Resurrection Bay, about 500 ft longer than the prevailing dock that should be changed due to its age, railroad officers stated.
The longer dock will allow cruise firms to herald ships that may haul round 4,500 passengers, greater than the roughly 2,500-passenger ships that now attain Seward, stated Invoice O’Leary, Alaska Railroad president.
These large ships presently go to Southeast Alaska, however they don’t cross the Gulf of Alaska to go to Southcentral Alaska, he stated.
O’Leary stated the larger ships will imply extra guests not only for Seward, however for locations similar to Anchorage or Fairbanks, he stated.
“It’s a essential challenge for not solely the cruise business, but in addition all the customer business in Alaska,” O’Leary stated.
Enterprise and political leaders in Seward stated they help the plans. However the prospect of an even bigger footprint for the cruise business has some residents within the bayside city of two,800 carefully watching developments.
[Earlier coverage: Tourists and cruise ships are ready to return to Seward. But is Seward ready for them?]
The challenge will likely be principally full in two summers, and finalized in 2025, railroad officers say.
The cruise ship dock improve a part of an even bigger effort to improve the railroad’s infrastructure locally. An growth of the freight dock is up subsequent, to be completed in 2027.
The docks are important transportation hyperlinks for the state, O’Leary stated. He stated the enhancements will even help industries similar to development that ship supplies to Seward for distribution throughout Alaska.
“It’s a big sum of money for a city of that dimension and for a railroad of our dimension,” O’ Leary stated.
The guts of the plan is the substitute of the passenger dock. It was initially a freight dock, in-built 1966 because the railroad upgraded its amenities following the Nice Alaskan earthquake two years earlier.
The dock remains to be secure, however its pilings are corroding, stated Clark Hopp, the railroad’s chief working officer. It has handed the usual design lifetime for a marine challenge.
“It has served us effectively,” Hopp stated. “However as we wish to say on the railroad, it’s in hospice care. It’s going to die.”
The railroad is engaged on an settlement with Royal Caribbean for that cruise firm to function the brand new dock’s long-term anchor tenant, O’Leary stated.
Wendy Lindskoog, a Royal Caribbean vp for West Coast operations, stated the settlement, nonetheless beneath negotiation, might cowl two or three many years.
The dock growth will help Royal Caribbean’s plans to carry its new Quantum-class ships to Seward, she stated. The ships are bigger and extra energy-efficient than earlier ships, she stated. Two of the ships visiting Southeast this 12 months are the Quantum of the Seas, with capability for 4,900 visitors and Ovation of the Seas, with capability for 4,200 visitors.
Alaska and Seward are widespread with visitors, she stated.
“Our firm has an awesome curiosity in rising in Alaska,” she stated. “Our visitors love the vacation spot.”
In 2019, about 230,000 individuals disembarked in Seward. They have been a part of the 1.3 million cruise visitors to go to the state that 12 months.
Trade officers have stated that statewide document may very well be damaged this 12 months, after massive cruise firms confronted two years of zero-to-limited calls in Alaska throughout the COVID-19 pandemic.
[Tourists are returning to Alaska this summer. Will there be enough workers to manage them?]
As a part of the passenger dock growth, the railroad can be planning a brand new terminal constructing, the place cruise visitors collect as they put together for his or her land journey in Alaska.
If wanted, the railroad will take a look at growing its capability to move extra visitors from Seward to Anchorage and elsewhere, O’Leary stated.
The Alaska Legislature superior the cruise dock challenge this session, approving a invoice for a $60 million bond.
The railroad will cowl the remainder of the price with money, railroad officers say. The bonds will likely be repaid over time with dock person charges.
Seward is basically excited in regards to the alternative for extra guests locally and modernized amenities on the port, stated Kat Sorensen, head of the Seward Chamber of Commerce and Customer Middle.
“Will probably be a boon for Seward typically,” she stated.
Trent Gould, proprietor of Kayak Adventures Worldwide, an area kayak guiding enterprise, stated he’s involved that greater and extra cruise ships might damage Seward’s small-town appeal.
“As a tour operator, we acknowledge the significance of tourism and we need to handle it in a sustainable manner with individuals having a say in that progress,” he stated. “When the cruise ships are available, these values don’t at all times align.”
Seward Vice Mayor Sue McClure stated many cruise visitors typically head straight to Anchorage by rail or bus. That reduces the necessity for extra seasonal employees or housing to help them, an particularly pressing problem now as Seward offers with ongoing labor scarcity points.
Whereas some cruise visitors will spend time in Seward, she stated the group can adapt to any labor points or different issues that may come up.
One profit is that the bigger cruise ships, if they arrive, will create extra work for the native longshoremen that help them, she stated.
“I’ve no worries about what they’re proposing,” she stated of the railroad’s plans.
As for the railroad’s plans to develop the freight dock in Seward, it’s going to greater than double in dimension after it’s widened and lengthened. Will probably be about 1,000 ft lengthy when the work is completed.
The freight dock growth is a part of a $25 million challenge, with a 2020 grant from the U.S. Maritime Administration paying for many of it.
The growth will enable extra environment friendly motion of the freight that arrives in Seward, similar to fracking sand and pipes for the oil business, officers stated.
The railroad says it’s going to deal with constructing the passenger dock first, then the freight dock.
The phased strategy is required partially to keep away from disrupting cruise ship exercise in summer time, the railroad officers stated.
Anchorage Every day Information journalist Marc Lester contributed to this report.
• • •