KANSAS CITY, Mo. — The Kansas City, Missouri, City Council voted Thursday to begin an effort to restore the once-grand Federal Reserve building on Grand Avenue in the city’s downtown.
Courtesy of Alicia M Brady, Urban Alicia Photography
The council approved an ordinance that directs KCMO City Manager Mario Vasquez to begin the receivership process “for the vacant nuisance property known as the former Federal Reserve Bank of Kansas City.”
The building closed in 2008 and neglect followed the closure, according to a docket memo to the city council that lays out problems with the building.
You can read the docket memo below.
“The site’s vacancy and nuisance conditions directly and increasingly depreciate the value of nearby properties and depress regional commercial activity; and residents and property owners near the site lament the nearly two decades of inactivity and decomposition, citing both aesthetic and security concerns involving the site’s crumbling exterior, graffiti covering the interior, broken glass and refuse strewn throughout, exposed ceilings with materials left dangling, an unsecured elevator shaft, and the site’s serving as a haven for squatting, fires, and other chronic nuisance activities; and the city has received multiple reports of property violations at the site over time, including falling debris and people entering through unsecured entrances, and the current developer’s failure to prevent and remediate these nuisances violates Code of Ordinances Sections 48-31 and 48-46(c), among other provisions.”
A developer bought the site in 2013, and the city approved a financial incentive deal in 2016 for the developer to build a 284-room hotel, a 450-space parking garage and a 40,000-square-foot family entertainment center.
The cost of the development was estimated at $182 million, but after investing $42 million in asbestos removal and interior demolition by April 2021, no other progress has been made on the project.
In 2022, the current developer got a temporary restraining order to avoid foreclosure after a default notice “alleging failure to maintain property insurance, unpaid property taxes, and outstanding mechanic’s liens,” according to a docket memo.
KSHB 41 News reached out to Alicia Brady, an Iowa-based photographer whose work includes photographs of the building’s decay.
Courtesy of Alicia M Brady, Urban Alicia Photography
“I was thrilled to learn that the mayor came across my post and photographs and that they helped spark action toward getting the former Federal Reserve building back on track for rehabilitation,” Brady said in an email to KSHB 41 News. “As someone who has been documenting abandoned and historic buildings since I was 15 years old, it’s incredibly rewarding to know that my work may have played a small part in preserving such an important piece of Kansas City’s history.”
KCMO Mayor Quinton Lucas posted on LinkedIn about Thursday’s council action.
“Since 2008, the old Federal Reserve Bank building has sat empty, left open to the elements, vandals, fires, neglect and decay,” Mayor Lucas said. “ No more. We’re taking action to ensure accountability from property owners and new life in this tower in the heart of our downtown.”
—
Missouri
One dead, hundreds rescued in devastating Missouri flooding – UPI.com
July 11 (UPI) — One person was found dead and hundreds evacuated in Missouri after an intense day of flash flooding across the state, authorities said Saturday.
More than 350 people were rescued in Iron, Reynolds and Crawford counties on Friday as floodwaters rapidly took over the area.
Officials said 250 of those were staff and children at Camp Taum Sauk, all of whom were safely evacuated. Another 100 were water rescues.
“It was very harrowing,” Jennifer Box, mother of of two you boys at the camp, told The New York Times. “We knew they were safe, but we didn’t know how to get to them, and that’s kind of your worst nightmare.”
One Crawford County woman, Faith Gregory, was found dead a mile downstream from her home in Huzzah Creek, officials said.
Authorities said Gregory was swept away after part of her home collapsed in the floodwaters.
“It’s definitely not the outcome we were hoping for, but it’s a tragic reminder of how strong Mother Nature can be and how forceful it can be,” Missouri State Highway Patrol Sergeant Eddie Young told FOX Weather.
The region was battered by more than 12 inches of rain, leaving many area residents remained strained throughout Saturday.
“But they’re OK,” spokeswoman Kate Moore, of Missouri Region C, told ABC News. “They’re just stranded because the roads are washed away. We have a lot of damage — the trees, buildings, a lot of things have gone and ripped the roads away.”
Missouri
Missouri pushes for more nuclear energy to power the future
Driving through the winding roads of Callaway County, often visible in the distance is a massive, 553-foot-tall concrete structure emitting what looks like white clouds.
“A lot of people think that’s smoke coming out of the top; it is not. That is water vapor,” said Travis Hart, manager of the Callaway nuclear power plant that produces 15% of Missouri’s electricity.
“The next structure that you see, this big rounded dome … that is the reactor building itself,” Hart said.
The single nuclear reactor near Fulton was built in the late 1970s and began generating electricity in 1984. Initially, the site was designed with two reactors in mind. But Hart said plans for a second unit came to a halt in the early ’80s due to decreasing electricity demand and rising costs.
Now, more than 40 years later, energy demand is growing due to increased manufacturing, adoption of electric vehicles and the development of AI data centers.
In a scramble for more power, tech companies and utilities are restarting formerly shuttered nuclear power plants, such as Three Mile Island in Pennsylvania. In states like Missouri, politicians are eager to find ways to build new ones and expand existing plants like the one in Callaway County.
Debates about how to pay for the multibillion dollar projects resurfaced in the Missouri legislature this spring. While cost is the first hurdle to creating a new fleet of nuclear power plants in America, the actual construction of the facilities is the second.
Early this year, Missouri Gov. Mike Kehoe signed an executive order that creates the Advanced Nuclear Energy Task Force to “evaluate and guide” the state’s “strategic approach to nuclear energy development.”
Lost skills
The majority of the nuclear power plants in America were built between the 1960s and 1980s. Construction slowed in response to energy demand leveling out, increased safety regulations and public perception of nuclear power souring after the Three Mile Island accident.
Speaking at the University of Missouri in May, Director-General of the federal Nuclear Energy Agency William Magwood said building nuclear power plants is a skill, and America has gotten rusty.
“We used to be really good at building plants back in the ’60s and ’70s. How do we reconstruct that? That’s going to be a real challenge,” Magwood said.
The only new nuclear power facilities built in America in recent decades are the third and fourth reactors at the Vogtle electric plant near Waynesboro, Georgia. While the reactors came online in 2023 and 2024 and produce more than 1,000 megawatts of power each, the project was billions of dollars over budget and years behind schedule.
Magwood said a lot of what boggled the Vogtle construction was the lack of institutional knowledge about building nuclear power plants.
“We just didn’t know what we were doing,” he said. “We hadn’t built a nuclear plant in a generation. We didn’t have people who knew how to do it. We didn’t have the infrastructure. We didn’t have the supply chain. The regulator didn’t know what the hell they were doing. I was there, so I know.”
In South Carolina, efforts to construct a new nuclear power plant were abandoned after billions were spent and the company behind the project went bankrupt.
Kurt Schaefer is tasked with ensuring Missouri can avoid similar blunders.
The longtime politician and public servant has been dubbed “the leader of Missouri’s nuclear power renaissance” by UM System President Mun Choi, who has been enthusiastic about advancing nuclear power by hosting national energy leaders on campus in recent years.
In May, Kehoe appointed Schaefer as head of the state’s new nuclear power task force, a group of representatives from utility companies, higher education institutions, politicians, state utility regulators and trades workers all charged with finding a way to make new nuclear power a reality.
Schaefer said the first step to establishing more nuclear power in the state is finding the cash.
“It’s all about money,” he said. “It is expensive up front to build a plant and unless the federal government steps up, I just don’t see it happening.”
In June, the federal Department of Energy announced $17.5 billion in loans for utilities and energy companies to build 10 large-scale commercial nuclear reactors.
Schaefer wants one of those reactors to be in Missouri, ideally near the existing nuclear plant in Callaway County.
“We are really behind the eight ball here in the United States on nuclear power, but you’re seeing a big effort, particularly from the federal government, to move us in that direction,” he said.
As electricity demand continues to climb, Schaefer believes nuclear power is the best way for Missouri to meet that demand. The zero-carbon plants can generate energy around the clock, unlike solar and wind power that need the right conditions to produce power.
Plus, given the longevity of nuclear power facilities, Schafer sees them as a good investment. To him, a robust power supply means a booming economy.
“This is our future, this is what we have to do to keep Missouri economically viable and that’s what we’re gonna do,” Schaefer said.
Who goes first?
The ballooning costs of nuclear power plants isn’t a new issue.
“Any project that big takes years to complete and things may change in the meantime,” said Victor McFarland, University of Missouri energy historian. “The costs of your supplies might go up, the cost of labor might go up.”
Decades ago, when many of America’s atomic energy centers were built, inflation was high and budgets stretched beyond initial figures.
“So the original estimates for the construction of these plants that were true, say, in 1970, they weren’t true anymore in 1975 or 1980,” McFarland said. “There were big cost overruns.”
Now, as the world turns away from fossil fuels, Magwood said nuclear capacity needs to triple to meet the net zero by 2050 goals. Currently, the nuclear power industry does not benefit from economies of scale. Because new nuclear projects are rare, costs are high and supply chains aren’t fully developed, adding to the overall risk of the endeavor.
“One of the big problems is nobody wants to be first … everybody wants to go fourth,” Magwood said. “Believe it or not, that doesn’t work very well. Somebody has to bite the bullet. Somebody has to take the risk. And what I think the industry would really like would be if the government somehow put a safety net under the first projects.”
Ameren Missouri has been clear about its goals to develop additional nuclear power. The company is planning to add 1,500 megawatts of atomic energy to its portfolio by 2045.
Callaway nuclear plant manager Travis Hart is an electrician by trade and first set foot at the facility 25 years ago when he was hired to work on the refueling crew. He said that’s when he fell in love with the place.
“When I walked in here and saw the equipment, how it fits together, how it works, how the design was, it was just extremely interesting to me,” Hart said.
There are a number of reasons the Callaway site is suited for expansion, Hart said. The location has access to the power grid, water from the nearby Missouri River, and a largely supportive local community that fills the plant’s roughly 750 permanent jobs while the company pays $9.8 million in annual property taxes to Callaway County.
The Callaway Energy Center’s current operating license extends through 2044, and Hart is confident the company will receive approval to operate beyond that date.
“I tell my people here all the time, … ‘this is important, so we got to get it right, and we got to do a good job of it, and it’s okay to be proud of it, because it makes a difference,’” Hart said.
In the coming years, the state’s new nuclear power task force will assess Missouri’s readiness to provide the workforce, policies and supply chain needed to create the “nuclear power renaissance.”
This story was originally published by KBIA and shared through the Missouri News Network.
Missouri
Flash flooding traps hundreds of people in rural Missouri
-
Arizona19 seconds agoCardinals Mailbag: Latest on Jacoby Brissett, Carson Beck, and Arizona’s QB Future
-
Arkansas7 minutes agoArkansas tips its hat to blues pioneer Larry “Totsie” Davis in England dedication
-
California10 minutes ago‘Explosive diarrhea’ parasite surfaces in California as health officials fear statewide surge
-
Colorado15 minutes agoThis Quiet Colorado Town Is An Underrated Gem For Nature Lovers
-
Connecticut22 minutes agoCar catches fire in Trumbull
-
Delaware25 minutes agoPower outage number tops 13,000 in Delaware County as storm hits
-
Florida30 minutes agoFlorida top-ranked signee selected in Round 4 of MLB draft
-
Georgia37 minutes ago3 Georgia baseball players taken in MLB Draft opening day