MORGANTOWN, W.Va. — The heavily-publicized NextEra Energy MidAtlantic Resiliency Link (MARL) project being considered by the state Public Service Commission may have the Monongalia County Commission as an intervenor.

Tom Bloom

The county commission unanimously agreed earlier this week to consider the move.

The commission heard more more information at this week’s meeting from groups opposing the project that will encompass parts of three states and cut through nearly half a dozen counties in West Virginia.

Commissioner Tom Bloom read from a letter.

Advertisement

“On behalf of all the residents in the four affected counties, (the commission is asked) to please help us fight the proposed transmission line and consider Mon County becoming an intervener,” said Bloom. “So I did want to put that on the record.”

The approximately 107-mile-long MARL project would be powered in Greene County, Pennsylvania. The 500-kilovolt line would support data center development in Virginia and would also include crossings in parts of Maryland, with the state portion expected to cost approximately $482 million.

Sean Sikora

According to Monongalia County resident Juliet Marleer, one of many who have vocally opposed the project moving forward, aspects related to costs have continued to change in the negative as well as additional parameters that would make areas affected by the planned power line much worse. Aspects of the project that have been pointed out by organizations like West Virginia Against Transmission Injustice in recent weeks.

“It has gone up from the original $440 million to $1.16 billion (price tag),” said Marleer. “So right now, my question is, how do we find out exactly what’s going on here?”

Bloom said he’s concerned about recent adjustments about the width of property needed for the line.

“That’s the one that bothers me the most, the siding corridor width is 200 to 500 feet, however, with aerial easement blowouts, the maximum width could be 715 feet,” said Bloom.

Advertisement

The county commission plans to make a decision on intervenor status in the near future. The state PSC is expected to schedule public hearings on the MARL application as early as May or June.

“I think that the commission can play a part in helping with that lift in regard to making sure that we have competent legal counsel representing us and our citizens,” said Commissioner Sean Sikora. “It’s been on our list of things to do and something we’ll certainly have a conversation about.”

An informational meeting for those in opposition of the MARL project will be hosted at the Cheat Lake Volunteer Fire Department sometime later this month. A specific date has not been announced.



Source link

Advertisement

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Trending

Exit mobile version