MDOT updates improvement projects in central Mississippi

Published

on


A design-build venture calling for the widening of the Interstate 59/20 bridges over State Route 19/39 and the bridge over sixty fifth Avenue in addition to the removing of bridges over Knight Parker Street, is making headway by the town of Meridian. It additionally features a roadway lighting system improve by Meridian alongside I-59/20.

Crews have accomplished visitors shifts on the sixty fifth Avenue web site and the SR 19/39 bridge web site. Pile driving efforts are full and crews proceed pouring concrete at every location. The Knight Parker Street bridges have been changed with roadway fill, and widening of the shoulders on the sixty fifth Avenue bridge and SR 19/39 websites is underway. The reducing of SR 19/39 has been accomplished apart from the ultimate carry of asphalt.

“These enhancements are essential and lengthy overdue for Lauderdale County,” stated Simmons. “The design-build side of the venture expedites the flexibility to get the design accomplished as quickly as doable, and every a part of this venture will additional improve security and effectivity for motorists and business visitors in Meridian.”

The $24.4 million design-build venture was awarded to Key Building Firm of Madison with an anticipated completion date of summer season 2023.

Advertisement

Freeway 19 enlargement venture in Neshoba County

The enlargement of Freeway 19 from two to 4 lanes from Tucker to Philadelphia continues in Neshoba County. Asphalt paving operations have begun, and momentary development signage has been put in. Different work underway consists of clearing and grubbing, topsoil removing, the set up of abrasion management objects, excavation, field bridge development and pipe set up.

Site visitors has steadily elevated alongside the SR 19 hall. Since 2017, the common annual day by day visitors alongside this stretch of roadway has elevated from 5,600 to six,600 and continues to be rising. Along with increasing to 4 lanes, the brand new grading will provide smoother driving situations, exhibiting important progress all through the realm.

A number of native roads will probably be realigned to tie into the brand new 4 lane roadway, making it a safer and extra handy journey expertise. North Tucker Street was lately reopened to visitors after crews accomplished new alignment onto SR 19. The $36 million contract was awarded to W.G. Yates and Sons Building of Philadelphia. The venture is anticipated to wrap up in 2024.

Slide repairs on Interstate 20 and Interstate 220 in Hinds County

A venture to restore two landslides on I-20 east of the Large Black River and one landslide on I-220 on the U.S. 80 interchange in Hinds County is underway. Filth work is underway on the primary web site, and pile driving in any respect three websites has been accomplished.
Crews anticipate finishing this restore summer season 2023. The $955,000 venture was awarded to Joe McGee Building Firm, Inc. of Lake.

Mill and overlay of State Route 468 in Rankin County

A venture calling for the mill and overlay of 11 miles of State Route 468 from Deeb Road to U.S. 80 continues in Rankin County. This consists of the mill and overlay of 0.4 miles of U.S. 80 from SR 468 to Louis Wilson Drive. Different work objects embody repairing failed areas, upgrading visitors sign detection to radar, and upgrading guardrail.
Failed space repairs are full. Milling and paving operations are at present underway. The almost $8 million contract was awarded to Superior Asphalt of Byram.

Advertisement

Freeway 487 bridge replacements proceed in Leake County

The substitute of three bridges on State Route 487 between Tuscola and State Route 35 in Leake County stays underway. The northernmost of the three bridges is full and has been opened to visitors.
On the second bridge, crews are at present working to drive piles and pour bridge caps. Earthwork and clearing operations are ongoing on the remaining two websites.

The $9.6 million venture was awarded to L&A Contracting Firm of Hattiesburg. Work is anticipated to be accomplished by early 2024.

Mill and overlay of State Route 463 in Madison County

A venture to mill and overlay 1.5 miles of SR 463 from the tip of the two-lane part to east of Foremost Road in Madison County is underway. Different work consists of upgrading the present visitors sign programs to radar detection and concrete sidewalk repairs.

Advertisement

Building indicators have been put in, and visitors sign detection has been upgraded. Sidewalk repairs and ADA ramps are full, and the restore of failed areas has been accomplished. Milling and paving operations are almost full, apart from re-paving the driveway and facet highway connections remaining.

The $5.1 million venture was awarded to Dickerson & Bowen of Jackson. Remaining work is anticipated to be accomplished this winter.

Mill and overlay of Freeway 35 in Scott County

A mill and overlay of roughly 8 miles of State Route 35 in Scott County from the Smith County line to I-20 is underway. All paving is full. Remaining work consists of putting shoulder gravel and thermoplastic stripe alongside the venture.

The $6.4 million contract was awarded to APAC, Mississippi. The venture is anticipated to be full by the tip of 2022.

Advertisement

Lottery funded mill and overlay of Freeway 18 underway in Copiah County

A lottery funded mill and overlay of 18 miles of State Route 18 from the tip of the Copiah County line to the start of the four-lane part close to Raymond is underway. The scope consists of repairing failed areas, repairing and changing cross drainpipes and widening parts of the roadway.

The almost $8 million venture was awarded to Superior Asphalt, Inc. of Byram. The estimated completion date is summer season 2023.

Bridge preservation venture on Freeway Route 145 in Noxubee County

A bridge preservation venture on State Route 145 over Horse Hunters Creek in Noxubee County is underway. Work consists of portray the substructure, repairing beam ends, epoxy repairs of failed areas, undersealing, putting rip rap stabilization and cleansing bridge caps.

Advertisement

The $646,000 venture was awarded to Century Building Group of Ridgeland. The venture is anticipated to wrap up summer season 2023.

Lottery funded mill and overlay on Freeway 22 in Madison County

A mill and overlay of three miles of State Route 22 from the start of the five-lane part to U.S. 51 in underway in Madison County. Building indicators have been put in. All sidewalk repairs and ADA ramp set up is full.
Remaining work is anticipated to wrap up summer season 2023. The $3.8 million contract was awarded to AJ Building, Inc. of Jackson.

Sign upgrades on Freeway 25 in Hinds County

A venture to improve the present sign detection gear to radar detection on SR 25 from I-55 to State Route 475 is underway. The contractor has accomplished work on a brand new sign pole and is awaiting remaining supplies.

Advertisement

The $398,000 venture was awarded to Lewis Electrical Inc. of Flowood. Work is anticipated to be accomplished this winter.

Preconstruction actions are underway for Freeway 25 widening in Rankin County

MDOT was allotted $4 million by the Mississippi Legislature to help in preconstruction actions on a venture to widen State Route 25 from Grant’s Ferry Street to State Route 471 in Rankin County. Widening the roadway from 4 to 6 lanes will finally develop capability and enhance security and mobility alongside the SR 25 hall.

“This cash will go in direction of actions akin to survey, hydraulic evaluation, roadway and bridge design, Proper of Manner acquisition and utility relocation. As soon as these things have been accomplished, as funding turns into out there, we will transfer to development,” stated Simmons. “Though development of this widening venture depends upon future funding, we’re working intently with Flowood Mayor Gary Rhoads and the Legislative management to make sure we could have the required funding on the applicable time.”

This 3.5-mile stretch of SR 25 sees a mean of 17,000 automobiles day by day. With an ever-growing improve in visitors, the design will embody security enhancements all through the SR 25 hall.

Advertisement

“I’d wish to thank Senators Josh Harkins, Dean Kirby and the Home members representing Rankin County for helping with funding to widen SR 25. With a preconstruction estimate of $5.5 million, this $4 million will go a good distance in funding the start levels of this essential infrastructure enchancment venture,” stated Simmons. “That is progress for our state and its transportation infrastructure as we work in direction of discovering revolutionary methods to construct and preserve a secure and dependable transportation community for future generations.”



Source link

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Trending

Exit mobile version