Iowa’s planned $125M water trail project could get a reboot

Published

on


Organizers of a $125 million Iowa water recreation path undertaking are looking for formal permission to downsize the scope of labor required below a federal grant.

Why it issues: The Iowa Confluence Water Trails (ICON) proposal — one of many largest pending public tasks within the space — will add facilities like boat launches and whitewater runs all through central Iowa rivers or creeks.

  • However a few of its first items are anticipated to be delayed for years and its price ticket retains rising due partly to inflation and provide chain points.

State of play: The undertaking was awarded a $25 million federal grant in late 2019, largely for work alongside a 5-mile stretch of the Des Moines River by means of downtown.

  • The primary part consists of modifying a low-head dam at Scott Avenue to make it safer for recreation and developing river entry factors at Prospect Park, Birdland Marina and Harriet Avenue.
  • Now organizers inform Axios they plan to ask federal officers Monday for permission to scale down the work.

Particulars: The revised proposal will nonetheless cowl the Scott Avenue dam and a revised portion of Harriet Avenue, Des Moines Space Metropolitan Planning Group (MPO) spokesperson Gunnar Olson tells Axios.

  • The Birdland and Prospect Park items could be accomplished in 3-5 years, relying on how a lot cash is obtainable then, Olson says.

Catch up fast: The preliminary two makes an attempt within the final 12 months to contract the primary part failed — one resulted in no bids and one other got here again with a single $73 million price ticket, $34 million above estimates.

  • Des Moines Councilperson Joe Gatto, who’s additionally a member of the MPO’s government committee, had warned earlier this 12 months that the undertaking’s funds may unravel if a second try and contract out the primary part failed.

What they’re saying: Gatto renewed his concern in an MPO assembly final month, telling the board that native governments are in a tough place and unlikely to allocate extra money for the undertaking.

  • Maggie McClelland, ICON’s director, instructed Axios Friday that they don’t seem to be in a position to estimate how a lot the undertaking would value if the revisions are accepted till the primary phases are bid out once more.
  • All of the items are nonetheless within the plan, McClelland emphasised.

The underside line: The water undertaking has hit some snags however organizers guarantee us they will not sink Iowa’s ICON.

ICON Water Trails consists of greater than 150 miles of rivers and creeks in Central Iowa. Map courtesy of ICON



Source link

Advertisement

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Trending

Exit mobile version