Connect with us

Alaska

Port of Alaska cargo terminal construction could be delayed due to lack of contractor bids

Published

on

Port of Alaska cargo terminal construction could be delayed due to lack of contractor bids


As the Municipality of Anchorage presses forward with the massive modernization project at the Don Young Port of Alaska, city officials say that construction of the first cargo dock terminal will likely be delayed, and much of that work won’t start next summer as previously intended.

That’s because the city did not receive any bids from construction companies after undergoing a monthslong procurement process to select one.

“We anticipate a delay of one season on the actual dock construction. There are other portions of the project, things like the electrical systems — that work should be able to proceed on schedule,” said Jim Jager, the port’s spokesman.

Advertisement

The city is now retooling its bid proposal package in order to make it more attractive to potential bidders, Municipal Manager Becky Windt Pearson told the Anchorage Assembly last week.

Meanwhile, the Assembly is set to vote on a slate of measures related to the modernization project.

During a Wednesday meeting, Assembly members will consider whether to finalize the expanded construction design for cargo dock terminal two; whether to authorize $180 million to $250 million in proposed bonds, much of which would fund the next phase of work; and proposed tariff increases to pay for those bonds.

The port’s infrastructure is failing, threatening a critical piece of the state’s supply chain, and port officials have emphasized urgency in finishing at least one cargo terminal as quickly as possible.

Despite the contracting holdup, city officials say they’re working to keep the project moving during the next construction season.

Advertisement

“We don’t, in any way, expect that the project is paused,” Bill Falsey, chief administrative officer, said in an interview.

For example, the city is looking to construct an electrical substation next season, and other preparatory work for the cargo terminal could proceed, he said.

“Our intent is that we will reissue the request for proposals, get vendors and award a contract (so that) the construction seasons are used and that we are still making progress,” he said.

Without the capital improvements, the Port of Alaska “will be required to be shut down within ten years,” according to a memorandum for the bond proposal.

Officials have been giving the port a similar lifespan estimate for years, saying in 2017 that the docks only have about 10 years left.

Advertisement

The port handles about 75% of the state’s inbound cargo, including goods such as food, fuel, construction supplies, vehicles and tools. About 90% of Alaskans rely on goods that come through the port.

Estimates clock the total cost of the modernization project at somewhere between $1.8 billion and $2.2 billion.

No bid

In January, the city began a pre-qualifying process for potential bidders on a contract to construct cargo dock terminal one. It identified two: Manson Construction and Kiewit Corp., Windt Pearson said. But when the bidding window closed in September, no bids came in.

The administration is “working as quickly as possible to gather feedback, specifically from those two qualified bidders together, from our project management team and from our legal team, on how we might tweak the terms of the construction deal to make it enticing, to make sure that we have bidders this time, make sure we can get the project back out in the street as quickly as possible,” Windt Pearson said.

City officials say there are likely a lot of factors as to why no bids came in. They include several big risk considerations, such as extremely long “lead times” for acquiring expensive materials — costs that a contractor would have had to front until reimbursed by the city for its work.

Advertisement

“I think part of it is our project is really big and complicated and has lots of risks, everything from weather, short construction seasons, difficult logistics, challenging permitting, that it just made it a really sticky project for people,” Jager said.

Another issue is that federal money for big transportation and energy projects is flowing and competition for contractors is high, he said.

“It’s a contractor’s market right now because there are a lot of big projects out there,” Jager said.

[$663M Arctic port delayed, frustrating Nome officials and Alaska congressional delegation]

Windt Pearson last week told Assembly members that the proposed bond sale would likely help alleviate some concerns from construction companies. The about $180 million from bond sales will fund work and payments related to the port in 2025.

Advertisement

“One of the pieces of feedback we heard from the potential bidders on the contract was, ‘We feel a lack of certainty that you’re poised to be able to pay for this.’ And so that is a factor also here, in terms of the timing. It’s a ‘chicken or the egg’ kind of question,” Windt Pearson said.

Increases to the tariff schedule will be passed on to consumers. Those increases will be in place for many years until the bonds are paid off, Falsey said.

However, the financial impact on everyday consumers will likely be relatively small. For example, the tariff on a barrel of petroleum products would increase to 19 cents in 2026.

“You do potentially at the gas pump start to see an effect, but it is pretty minor,” Falsey said.

For cargo, the tariff would rise to $8.29 per ton, impacting the price of items from groceries to building materials, vehicles and heavy equipment.

Advertisement

Final terminal design

Wednesday’s vote is expected to put a cap on a nearly two-year-long debate over whether to move ahead with an expanded, more expensive design for the two cargo terminals.

An early design concept approved by the Anchorage Assembly in 2021 called for one wider cargo terminal to be built for using cargo cranes to move freight, and a second, narrower terminal for handling “roll on, roll off” freight — freight that rolls off ocean freighters directly onto the docks.

Assembly members on Wednesday are slated to vote on whether to approve an expanded design: Cargo terminal two would be built to the same 120-foot width as terminal one. That would allow both docks to accommodate 100-gauge cranes, though roll-on, roll-off cargo could only be handled at terminal two under the design.

Last summer, the Assembly approved a measure that paved the way for the expanded, uniform width design for both terminals, but punted the final decision on terminal two’s design.

The port’s Design Advisory Board unanimously approved the terminal two design in June, and Assembly members appear poised to pass the measure. However, some have raised concerns about lacking “roll-on, roll-off” capabilities at both planned cargo terminals.

Advertisement

“At one point, the port director said that what the (municipality) needed, absent any of the other users, was full redundancy. This redundancy and resiliency at the port. We needed the two mirrored docks. And so that’s where I think this question is coming from,” Assembly Vice Chair Meg Zaletel said at the meeting last week.

Eric Adams, who oversees the port modernization as a project manager with Jacobs Engineering, advised that adding trestles for roll-on cargo to terminal one would delay construction due to additional permitting requirements, and it should wait until after both cargo terminals are built.





Source link

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Alaska

Alaska is reporting 18 in-custody deaths so far this year, tying a grim record

Published

on

Alaska is reporting 18 in-custody deaths so far this year, tying a grim record


Barbed wire fencing surrounds Goose Creek Correctional Center on Tuesday, Aug. 29, 2023 outside of Wasilla. (Loren Holmes / ADN)

The Department of Corrections this week reported the 18th death of an inmate this year, tying the record for the highest number of annual in-custody deaths in at least the past decade.

Kane William Huff, who had been imprisoned at Goose Creek Correctional Center near Wasilla, died Dec. 11, according to a DOC statement. Huff, 46, was serving a sentence for a 2018 conviction on two counts of sexual abuse of a minor, according to online court records. DOC officials said he had been in custody since 2015.

Huff was found unresponsive in the prison’s infirmary, where he had been housed, said Department of Public Safety spokesman Austin McDaniel. Alaska State Troopers, who handle in-custody death investigations, have closed their investigation and are awaiting autopsy results from the State Medical Examiner Office, McDaniel said. Troopers don’t believe Huff died by suicide or that foul play was involved, he said.

The last time as many people died in state custody was in 2022, when a record seven inmates also died by suicide, according to a department snapshot of deaths since 2015.

Advertisement

The Department of Corrections began consistently keeping inmate death statistics in 2001, said spokesperson Betsy Holley. The department also posts data showing in-custody deaths since 2015. That year, 15 people died while in DOC custody.

The state’s official count for 2025 doesn’t include the death of 36-year-old William Farmer, who died in a hospital in January after he was severely beaten by his cellmate at the Anchorage Correctional Complex the month before.

An upward trend of in-custody deaths in the past several years has alarmed some prisoner rights advocates and prompted state lawmakers to ask Department of Corrections officials to address the deaths in multiple hearings this year. The department has also found itself under fire for inmate suicides.

This year, at least four inmates have died of natural or expected causes, such as disease or a medical event, while at least five have died by suicide, according to information provided by Alaska State Troopers.

Officials have also said that a Spring Creek Correctional Center prisoner died of an overdose in April.

Advertisement

Another inmate, 53-year-old Jeffrey Foreman, died in July after being restrained by guards after an altercation with his cellmate at the Anchorage Correctional Complex.

[Correction: An earlier version of this story incorrectly described the year the Department of Corrections started consistently keeping inmate death statistics. It was 2001, not 2015.]





Source link

Continue Reading

Alaska

Hawaiian, Alaska airlines to use locally made biofuel | Honolulu Star-Advertiser

Published

on

Hawaiian, Alaska airlines to use locally made biofuel | Honolulu Star-Advertiser




Source link

Continue Reading

Alaska

LNG pipeline legislation debate divides Alaska lawmakers after consultant calls it ‘essential’

Published

on

LNG pipeline legislation debate divides Alaska lawmakers after consultant calls it ‘essential’


ANCHORAGE, Alaska (KTUU) Alaska lawmakers are divided over whether new legislation is needed for a liquified natural gas pipeline, with the state’s energy consultant calling it “essential” while some legislators say existing laws are sufficient.

“A successful project will likely require suitable enabling legislation from the state legislature, among other key prerequisites,” state-contracted energy consulting firm GaffneyCline, hired by the Legislative Budget and Audit Committee for up to $200,000 in April 2024, says in a document made public for the first time Monday.

The 62-page document, presented to the Legislative Budget and Audit Committee last month, concludes that legislation is essential for the pipeline to be viable but more needs to be done to get the project across the finish line.

“A detailed economic model of the project is required before the legislature can take an informed view as to the appropriate degree of government take that the project can sustain, and how this could evolve over time,” the document states.

Advertisement

Alaska’s News Source reached out to Glenfarne Tuesday for comment on who presents the economic model and when that model could be presented. Spokesperson Tim Fitzpatrick referred on the report for GaffneyCline.

“We will continue to work closely with the legislature to discuss policy issues that may affect Alaska LNG and work collaboratively on solutions that enable Glenfarne to provide Alaskans with affordable energy security as rapidly as possible,” he said in a statement.

The document’s release comes amid optimism from pipeline developers and federal officials but growing skepticism from some state lawmakers.

During a November Legislative Budget and Audit Committee which discussed the same topic, House Speaker Bryce Edgmon, NA-Dillingham, left believing “the upcoming 2026 legislative session could be dominated by policy measures related to advancing the Alaska gas line project.”

“We don’t have any of this,” Edgmon said last month, relating to laws GaffneyCline says are essential.

Advertisement

Rep. Mia Costello, R-Anchorage, former House minority leader and co-chair of the Alaska Gasline Caucus, said she believes legislation for the pipeline is not needed, citing previous legislative involvement.

“Large scale LNG projects around the world are successfully developed through commercial agreements, private capital, and existing regulatory processes not legislative intervention,” Costello said in a statement. “Alaska already has established permitting, taxation, and regulatory framework capable of supporting energy development. Legislative involvement risks introducing political uncertainty, delaying timelines, and discouraging investors who prioritize stability and market driven decision-making.”

However, Sen. Elvi Gray-Jackson, D-Anchorage, told Alaska’s News Source the policy measures currently in place are more than a decade old, created for a different project, and don’t easily mesh with the task in front of them today.

“When project leadership … and financial models change, it’s our responsibility to revisit the policy framework that governs the state involvement, and that’s what we’re going to do as a legislature,” Gray-Jackson said.

Legislative action?

The asks pipeline developers want in those policies could be steep.

Advertisement

On the list of asks is a concept called “fiscal stability,” essentially a promise if Alaska changes its tax or regulatory policies later, the state would make up any financial losses to investors, according to a GaffneyCline presentation shown to lawmakers on the Legislative Budget and Audit Committee.

Those guarantees can mean a “tax freeze” — locking in the current tax system for the life of the project — potentially 20-30 years, according to GaffneyCline’s presentation to lawmakers. If Alaska later raises taxes or imposes new regulations, the presentation said the state would have to compensate investors to maintain their original profit expectations.

Another ask is the lowering of property taxes for the pipeline, something GaffneyCline’s November presentation said could cost the project $1 billion and add 9% to the cost of delivered gas.

Gov. Mike Dunleavy plans to introduce a bill to lower property taxes for the pipeline, spokesperson Jeff Turner confirmed Tuesday. No other LNG bills are planned at this time, he added.

Time crunch

Whatever the legislature decides to do, they’ll need to do it quickly. The regular session convenes Jan. 20, and for the following 120 days, the process to create a package of policies and framework addressing LNG issues will likely be front of mind.

Advertisement

That comes after Glenfarne Alaska LNG set expectations in October that construction for the pipeline will begin in late 2026 and be operational by mid-2029.

“What Alaskans should take away from the report is that we need to hope for the best, but prepare for the situation not moving as fast as Glenfarne and the other players are thinking,” Gray-Jackson said.

Lawmakers have signaled a mixture of optimism for what the pipeline could create, but it comes with skepticism, too. Gray-Jackson said she was “cautiously optimistic.”

“Frankly, I don’t know where we’re at as far as the legislature is concerned because we haven’t gotten any real answers from Glenfarne,” Gray-Jackson said.

A Glenfarne spokesperson said last month they are active in providing information to the state legislature.

Advertisement

“Glenfarne is making rapid progress on Alaska LNG and regularly meets with legislators to provide updates and discuss important state and local policy considerations,” Glenfarne communications director Tim Fitzpatrick said. “We appreciate the legislature’s continued engagement to help make Alaska LNG a success for the state.”

“I understand the potential, huge, multi-generational impact of the state, as well as being very positive,” Sen. Bert Stedman, R-Sitka, told Alaska’s News Source following the Legislative Budget and Audit Committee meeting in November.

“Concentrating on the benefit of the project that we know, if it’s successful, it’s going to be very beneficial, and if it’s unsuccessful, it could be detrimental for generations.”

“Will the project even come unless we present the right scenario?” House Majority Leader Chuck Kopp, R-Anchorage, asked Nick Fulford, GaffneyCline senior director and global head of gas and LNG.

“You mentioned the buyers want 20–30 years of stability … our fiscal framework might be a little bit out of alignment, if I’m hearing you correctly,” Kopp said.

Advertisement

“If those things are all true, our needs, our situation, us being out of alignment, we’re going to have to look at possibly a reality that this line doesn’t even get [built],” the representative added.

Federal permits completed

The project completed 20 federal permits and environmental reviews last week, according to the Permitting Council, clearing what the governor called “the last major regulatory hurdle.”

“Alaska LNG received the major federal permits needed to proceed in 2020,” Fitzpatrick said. “Some of these permits have a five-year renewal cycle, which was completed last week and all of Alaska LNG’s major permits are current and in effect. Glenfarne has an ongoing process to maintain permits and authorizations for Alaska LNG.”

With the permits cleared, the pipeline inches toward a final investment decision (FID). Natural Gas Intelligence, a natural gas news provider, described an FID as “the last step of determining whether to move forward with the sanctioning and construction of an infrastructure project.”

A source familiar with the pipeline developments previously told Alaska’s News Source to expect an FID early next year.

Advertisement

“Alaska LNG will strengthen our economy, create long-term jobs, and provide reliable energy to Alaskans and our global partners for generations to come,” Dunleavy said.

“I am thrilled to see the Alaska LNG project finish federal permitting actions ahead of schedule,” said Permitting Council Executive Director Emily Domenech in the press release.

“This combined effort reflects our commitment to the State of Alaska and to achieving President Trump’s energy dominance agenda.”

Domenech visited the state alongside the congressional Natural Resources Committee in August, when Dunleavy signed a deal with the Trump administration aimed at bringing more resource development investment will come to Alaska.

LNG, however, was not heavily discussed at the meeting.

Advertisement
Governor Mike Dunleavy (right) shows a signed memorandum of understanding promising “improve(d) coordination and transparency in permitting major infrastructure projects across the state,” his office said.(Rachel McPherron)

“Completing federal permitting for Alaska LNG ahead of schedule shows how the Trump administration is restoring America’s Energy Dominance by cutting unnecessary delays and unleashing our abundant resources,” Interior Secretary Doug Burgum said in the release. “This project strengthens U.S. energy security, creates jobs for Alaskans, and reinforces our commitment to a permitting system that works at the speed of American innovation.”

National momentum

The federal push comes as as GaffneyCline’s presentation said both LNG supply and demand are expected to boom globally. Liquefaction, or the process of turning gas into liquid, is expected to increase by 42% by 2030, reaching about 594 million tons per year.

This summer, Dunleavy vetoed several bills and cut more than $100 million from the state budget, largely due to reduced state revenues from oil price declines.

“The oil situation has deteriorated,” Dunleavy said in a video statement before his budget was revealed. “The price of oil has gone down; therefore, our revenue is going down.

“Basically, we don’t have enough money to pay for all of our obligations. So, as a result of that, you’re going to see some reductions in this year’s budget.”

Advertisement

The pipeline project has support from both the state and federal levels. President Donald Trump has pledged to ensure an LNG project gets built “to provide affordable energy to Alaska and allies all over the world.”

On Jan. 20, Trump signed the “Unleashing Alaska’s Extraordinary Resource Potential” executive order, which the administration says prioritizes “the development of Alaska’s liquefied natural gas (LNG) potential, including the sale and transportation of Alaskan LNG to other regions of the United States and allied nations within the Pacific region.”

Despite the optimistic timeline, Alaska has seen multiple LNG pipeline proposals fail over the past two decades due to financing challenges, regulatory delays and market conditions.

Environmental groups and some Alaska Native groups have also raised concerns about the pipeline’s potential impact on wildlife and traditional lands.

See a spelling or grammar error? Report it to web@ktuu.com

Advertisement



Source link

Continue Reading
Advertisement

Trending