FOLLOWUP: Sound Transit Board finalizes $400+ million spending installment for West Seattle light rail

Published

on


Two weeks ago, we reported on the Sound Transit Board‘s System Expansion Committee recommending approval of actions to allot $406 million toward West Seattle light rail – the first big commitment after the ST3 plan revision that cemented ST commitment to WS. At this afternoon’s meeting of the full board, the actions all got final approval, as did a much-smaller installment of spending on Ballard light-rail planning.

Advertisement

(Here’s the full slide deck as presented at the committee meeting, also including the current WS light-rail cost estimate of around $5 billion.)

On the horizon, according to the most-recent ST email update, is work to advance the plan for the new cross-Duwamish River light-rail bridge, shown in this rendering:

(Sound Transit rendering)

That work on the south end of Harbor Island (in a parking lot at 1001 Klickitat, according to city docs) will see crews drill a test bridge shaft approximately 10 feet wide and 250 feet deep to better understand ground conditions,” ST says, to obtain “key information needed to finalize the bridge design.”





Source link

Advertisement

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Trending

Exit mobile version