Connect with us

Texas

ERCOT Warns Texas AI Power Boom May Not Materialize

Published

on

ERCOT Warns Texas AI Power Boom May Not Materialize


Texas is planning its grid around an unprecedented wave of AI-driven power demand that the state’s energy regulator says may not fully materialize on projected timelines.

In a recent filing to the Public Utility Commission of Texas, the Electric Reliability Council of Texas (ERCOT) projected statewide power demand could surge to nearly 368 GW by 2032 – more than four times the state’s current peak demand record of 85.5 GW. But the filing also contains an unusual warning from the grid operator itself.

“ERCOT has concerns with using the preliminary load forecast values for the Reliability Assessment and any other transmission and resource adequacy analysis,” the organization wrote in its April 2026 long-term load forecast filing

The organization added that it may seek adjustments to the forecast based on “actual historical realization rates or other objective, credible, independent information.” 

Advertisement

Interconnection Delays Push Texas Data Center Behind the Meter

ERCOT has already begun adjusting for realization risk internally. In its 2025 long-term load forecast report, the grid operator said the “average peak consumption per site was 49.8% of the requested MW” and applied that factor to projected non-crypto data center load additions in some planning models.

ERCOT President and CEO Pablo Vegas said the forecast reflects “higher-than-expected future load growth” tied to changing large-load planning dynamics.

Texas Developers Race Ahead of Grid Capacity

Texas has emerged as a key data center market, driven by its abundant land, competitive energy prices, and favorable regulatory environment. This combination has positioned the state as a magnet for hyperscale operators and AI infrastructure investments. The state is estimated to account for around 15% of all data center connectivity in the US.

Advertisement

Recent and proposed AI data center campuses tied to OpenAI, Oracle, Meta, Crusoe, CoreWeave, Soluna, and other hyperscale operators are reshaping Texas grid planning. Developers have proposed large campuses across North Texas, Abilene, West Texas, and the Houston corridor, many requiring hundreds of megawatts of capacity and, in some cases, dedicated onsite generation to bypass interconnection delays. That buildout pushed ERCOT’s non-crypto data center forecast above 228 GW by 2032.

Developers are continuing to pursue Texas aggressively because ERCOT still offers faster timelines and more flexible market structures than many competing regions. Several proposed campuses pair AI infrastructure with onsite gas generation, colocated power assets, or flexible-load arrangements to navigate mounting transmission constraints.

Texas Gets Tough on Data Center Power – Who’s Next?

Utilities across the US are grappling with AI-driven electricity growth, but ERCOT’s projections stand apart for both scale and uncertainty. PJM Interconnection, the nation’s largest grid operator, expects summer peak demand to climb above 241 GW over the next 15 years as data centers and electrification expand. ERCOT, by contrast, projects demand potentially reaching nearly 368 GW by 2032, driven largely by proposed non-crypto data center loads. At the same time, the grid operator openly questions how much of that demand will materialize on schedule.

Bigger Than Texas

Similar pressures are emerging elsewhere. In California, CAISO’s latest transmission plan cited “data center load growth” as a driver of major grid upgrades and described interconnection volumes as “unmanageable” before recent queue reforms. 

Advertisement

A recent Grid Strategies report reached a similar conclusion nationally, warning that the “data center portion of utility load forecasts is likely overstated by roughly 25 GW” compared with market-based deployment estimates. 

Ihab Osman, an independent strategist specializing in data center and other mission-critical infrastructure, said the distinction is less about “real” versus “fake” AI demand and more about “announced versus deliverable demand.”

Soluna Expands Texas Campus With 100 MW AI-Ready Data Center

“A large share of the current AI/data center planned load should be treated as paper megawatts until it is validated through physical gates,” Osman said, citing factors including site control, transmission deliverability, generation availability, turbine and transformer supply, permitting, financing, and credible energization schedules.

Osman said ERCOT’s forecast is best understood as “a stress-test map, not as a fait accompli build map.”

Advertisement

Separating ’Paper Megawatts’ From Real Demand

The filing shows Texas regulators and grid planners struggling to distinguish operating AI infrastructure from a rapidly expanding pipeline of proposed projects.

“The vast majority” of ERCOT’s projected load growth comes from submissions provided by transmission and distribution utilities, according to the filing. Those requests include hyperscale AI campuses, GPU clusters, and other large industrial loads seeking future grid capacity reservations.

Alison Silverstein, a former senior adviser to the chairman of the Federal Energy Regulatory Commission, said “a large proportion” of projects in ERCOT’s large-load interconnection queue have already been canceled, particularly among smaller developers facing long interconnection delays and high turbine and transformer costs.

Forecasts Collide With Physical Infrastructure Limits

ERCOT has also signaled that many projects may not materialize on the timelines shaping transmission planning.

The grid operator said summer 2026 peak demand is likely to land between roughly 90.5 GW and 98 GW – far below the preliminary 112 GW figure embedded in the long-term forecast. ERCOT said it appears “unlikely” that new large-load projects and existing site expansions will ramp quickly enough to push demand that high this year. 

Advertisement

The filing suggests uncertainty around AI-related load growth is beginning to influence broader infrastructure planning assumptions. By 2032, ERCOT projects non-crypto data centers reaching 228 GW of demand, compared with just 9 GW from cryptocurrency mining and roughly 3 GW each from hydrogen/e-fuels and oil-and-gas-related industrial growth. 

The move also suggests the regulator is no longer simply forecasting AI-driven growth, but also working to determine how much of the proposed boom can actually be financed, supplied, interconnected, and energized before utilities commit billions to long-lived infrastructure.





Source link

Texas

Social Security cuts could reduce monthly benefits by nearly $500

Published

on

Social Security cuts could reduce monthly benefits by nearly 0




Social Security cuts could reduce monthly benefits by nearly $500 – CBS Texas

Advertisement













Advertisement




























Advertisement

Advertisement

Watch CBS News


Millions of Americans who rely on Social Security could face significant benefit reductions within the next decade.

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement

Advertisement



Source link

Continue Reading

Texas

World Cup excitement builds as Team Sweden arrives in North Texas

Published

on

World Cup excitement builds as Team Sweden arrives in North Texas


With just eight days until North Texas hosts its first World Cup matches, fans are already gathering — including those who welcomed Team Sweden as the squad arrived in Frisco today. Supporters cheered outside the team hotel, many hoping to catch a glimpse of their favorite players. Sweden will train at Toyota Stadium as the region prepares for nine total matches, including a semifinal, all taking place at AT&T Stadium — temporarily renamed Dallas Stadium for the tournament.



Source link

Continue Reading

Texas

Texas cruise passengers complete hantavirus monitoring with no infections, state says

Published

on

Texas cruise passengers complete hantavirus monitoring with no infections, state says


The Dutch cruise ship MV Hondius is anchored off Praia, Cabo Verde, May 6, 2026. Cabo Verde on Wednesday carried out an air evacuation of three passengers suspected of hantavirus infection from the Dutch cruise ship MV Hondius, which had been anchore

Two Texas residents who were monitored for possible hantavirus exposure after traveling aboard an Antarctic cruise ship have completed their observation period without developing symptoms, Texas health officials said Saturday.

Advertisement

Antarctic cruise hantavirus outbreak details

What we know:

The Texas Department of State Health Services said the passengers reached 42 days since their last possible exposure to the Andes strain of hantavirus, the longest known period between exposure and the onset of symptoms. The agency said neither person showed signs of infection and no longer faces any public health recommendations related to the exposure.

Advertisement

Cruise passengers clear 42-day quarantine

The passengers had traveled aboard the MV Hondius, where several people later became ill with the Andes strain of hantavirus. The Texas residents had already left the ship and returned home before the outbreak was identified.

What they’re saying:

Advertisement

State health officials recommended monitoring for all passengers who had been aboard the vessel. In Texas, the two passengers were isolated at home and received twice-daily in-person evaluations by public health workers throughout the monitoring period.

“I’d like to thank the passengers for their willingness to collaborate with public health throughout the monitoring period,” Chief State Epidemiologist Dr. Varun Shetty said in a statement. “I would also like to thank the many dedicated public health professionals who worked on this situation and work every day to keep their fellow Texans safe.”

Hantavirus Symptoms and Transmission

Advertisement

What you can do:

Hantaviruses are typically spread through contact with infected rodents or their droppings. The Andes strain, found primarily in South America, is notable because it can spread between people, unlike most other hantaviruses.

Texas health officials did not report any infections among the monitored passengers.

Advertisement

The Source: Information in this article was provided by the Texas DSHS. 

HealthTexas



Source link

Advertisement
Continue Reading
Advertisement

Trending