Detroit, MI

Detroit People Mover closed through November for track replacements – WDET 101.9 FM

Published

on


The Detroit People Mover will pause operations for the next 11 weeks starting today, to allow for track replacements and other routine maintenance upgrades.

Over its 37 years in operation, the rail system has undergone regular maintenance based on federal best practices to maintain a “state of good repair.” About 20% of the rail track on the 2.9 mile, one-way loop will be replaced on nine curves and adjacent track as part of this latest round of upgrades, according to the Detroit Transportation Corporation (DTC).

This is the third rail replacement in the Detroit People Mover’s history, with different curves and adjacent track replaced during similar projects in 2008 and 2016.

The latest $4.985 million project — funded by federal and state grants — is scheduled to be completed in November, before Thanksgiving. The DTC anticipates the life expectancy of the new rail sections to be at least 15-30 years.

Advertisement

The Detroit People Mover averages around 113,000 trips per month, or 3,900 rides per day — depending on special events and weather conditions, according to the DTC.

Read more: Detroit People Mover gave 70,000 rides during NFL Draft

Trusted, accurate, up-to-date.

WDET strives to make our journalism accessible to everyone. As a public media institution, we maintain our journalistic integrity through independent support from readers like you. If you value WDET as your source of news, music and conversation, please make a gift today.

Donate today »



Source link

Advertisement

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Trending

Exit mobile version